Talking turkey today, but not really. Or not just turkey.
I recently shared project management concepts in Clutter 2.0, specifically Critical Path Management, and we are going to apply some of those to Thanksgiving Dinner!
I get questions this time every year about planning for getting holiday meals out of the oven and on the table on time. And while I am not a professional cook, I am a pretty good cook and have successfully hosted Thanksgiving dinners for the last 20+ years. I’m also great with time management, and this question is definitely a Time Management and even Project Management question!
Let’s face it, there are so many moving parts when it comes to these big meals!
In the same way that we can use project management and critical path management to remodel a kitchen, or hypothetically build a road like we do in my highway construction careers training program class, or manage our organizing projects at home or work, we can apply some of the same ideas to get Thanksgiving Dinner on the table as well. I’m excited to talk this through with you!
And of course, I am using Thanksgiving Dinner as an example, but you can apply these skills anywhere! So, let’s get to it!
To refresh, in very basic terms, Critical Path Project Management tells us:
Project steps need to happen in a certain order for success (precedent tasks);
Some steps can’t begin until the one before it is completed (path!);
Some tasks happen at the same time as other tasks (parallel);
Some steps can happen independently within the time given (slack or float!); and
When you put the steps in a path and create realistic time estimates for each task, there is NO WAY to finish the project in less time than the duration of the longest tasks end to end on the path.
Finally, factor in flexibility.
Close your eyes, and imagine the successful end product. Is it everyone eating together? Or is it the satisfied nap after the meal that I get to take because if you cook the meal, you’re not responsible for cleaning up? Too specific? Ok, maybe that’s just me.
Back to the successful end product. All the food read at the same time, everyone sharing something they are grateful for, and digging in to enjoy?
And what are those foods? Because, really, each of those food items is its own task or microproject. So first up, since we’re using Thanksgiving Dinner as the case study here, let’s assume there’s a turkey. Every family is different, but for us, there is likely mashed potatoes, corn casserole, maybe some sweet potatoes, stuffing for sure, a veggie of some type, maybe a salad, cranberry relish, gravy and desserts - of course! There must be pie.
In terms of project management, of course the longest part of the project, the part that determines the total duration of the project is obviously the turkey.
I just did some research:
(PLEASE do your own as you plan your holiday meal! I don’t want to be responsible for getting something wrong and then your family is clamoring for dinner if it’s late! )
For 20 people (and wanting some leftovers), we need 24-30 pounds of turkey. That might be one huge turkey, but we are choosing 2 smaller turkeys so they cook faster and more evenly.
In terms of cook time, multiple websites suggest 13 minutes per pound are required.
And the recommended cooking temperature varies, so do your own research!
In terms of today’s planning example, I’m going to say we’re cooking a 16 pound turkey which averages approximately 4 hours of cooking time, according to multiple websites.
Now, my friends, to say I need to cook my turkey for 4 hours - we all know we need to add time at the beginning and the end, right?! (yes, we do.)
At the start, we need prep time to preheat the oven, get the bird unwrapped and in the roasting pan, etc. So factor in an additional 15 minutes. AND, at the end, most resources suggest the turkey “rest” after it’s done cooking for anywhere from 20 to 60 minutes.
So, our 4 hours of cook time just became 5 hours and 15 minutes in duration. Yep, the turkey determines the duration of the project! All the other sides take much less than 5 hours and 15 minutes.
Now that we know the longest task, we need to ask - what TIME is dinner?! Because we have to start with the deadline in mind.
We have some scheduling parameters to consider when setting our dinner time. I will be hosting in Michigan, and we will have family members coming from Illinois, Ohio and Michigan. We don’t want dinner too early because people need time to travel. And we don’t want dinner too late because we don’t want the Ohio cousins to drive home in the dark in a turkey coma since one of them works on Friday. So, we’re aiming for midday, 1 pm EST.
We have our deadline and our longest task. We can work with this! Our critical path is falling into place!
Thankfully, when we’re making a meal, there's a lot of parallel tasks. The turkey can be in the oven, but there is room on the stove top to make some things, in crock pots for warming and on counters for more prep. And once the turkey comes out to “rest” until dinner time, we can use the oven to bake whatever else still needs baked, like the stuffing, corn casserole and sweet potatoes.
My preferred method to manage this project is a schedule or agenda, so I’ll go with that. And, to be honest, what will most likely happen is I will use post-it notes for each food item - prep / start / finish time and stick them on a kitchen cabinet. My husband and sons know what those post-it notes mean so they can grab one and complete the task!, and my siblings and in-laws get it, too!
Also on that cabinet door will be “buy ice for the cooler” or “open the wine” or “set up extra chairs” or “put leaves in the table”, etc.
So, what will that agenda look like? And yes, I will use this agenda to make the post-it notes!
1 pm Dinner Time (actually aiming for 12:45, for flexibility)
12:45 make the family stop playing cards and set the table
12:45 everything comes out of oven
12:30 15 minute warning to family to stop playing cards
12:30 rolls to oven to warm
12:30 take foil off stuffing
12:30 warm the gravy
Noon stuffing goes in the oven with foil (45 min total at 350)
Noon corn casserole goes in oven (45 min at 350)
Noon sweet potatoes to oven to bake
Noon adjust oven temperature for new items
Noon turkey comes out of oven
11:45 assemble corn casserole
11:30 microwave the sweet potatoes to start the cooking
11:30 assemble the stuffing
Have coffee with loved ones, set out apps and snacks as people start arriving!
10 am start mashed potatoes in crock pot to warm
7:45 am turkey goes in oven
7:30 am prep turkey and roasting pan
In critical path management, we talk about “float”, about those tasks that can be done anytime during the duration of the project. And the good news is that with float items, I can complete them the day before Thanksgiving to allow more flexibility the morning of!
WEDNESDAY,
Cook 1 turkey
Make make-ahead mashed potatoes
Dice / chop veggies and brown the sausage for the stuffing
Scrub the sweet potatoes and get them ready to microwave and then bake
Prep any breakfast or appetizers, like prepping fruit for a morning fruit salad or slicing cheese for cheese and crackers
Hard-boil eggs for breakfast and also deviled eggs
Find and clean serving dishes
Clean the kitchen well, fridge, too!
Tidy the rest of the house, make sure the house is ready for an influx of guests!
Other strategies:
DO NOT wait until Thanksgiving morning to try a new and complicated recipe.
If there is ANYTHING you can do ahead of time, do it.
Enlist aid / ask people to bring things.
People like to feel needed, and they like to feel a part of things. AND, they have mad skills of their own and may have a favorite item they would like to bring and share. And the answer to the offer is “Yes, Please!”!
Family members are bringing desserts, a salad, the rolls, beverages, appetizers, more sides and goodness knows what else. It’s a case of loaves and fishes - more goodness just keeps arriving that day, and we always have all that we need!
So, what did we learn? Yes, a big holiday meal may have a lot of moving parts, but it is a project just like many others. Which means, we can apply project management skills to the cooking and prep to ensure success!
Happy Thanksgiving!